A 42,000 m² warehouse complex cleared and the site handed over redevelopment-ready in twelve weeks.

Client
Infrastructure Development Group
Location
Rajasthan, India
Duration
3 months
Material handled
5,200 t
Project summary

Demolition and clearance of a redundant warehouse and logistics complex including portal frame structures, hardstanding, internal racking and below-ground services, with on-site concrete crushing for reuse in the redevelopment.

Scope of works

  • Racking and internal fit-out strip-out
  • Portal frame structural demolition
  • Hardstanding and slab removal
  • On-site concrete crushing and grading
  • Below-ground services removal
  • Site levelling and handover survey
The challenge

The redevelopment programme allowed twelve weeks from possession to construction start, with a fixed and heavily penalised handover date.

A live fibre trunk route crossed the site diagonally with no accurate record of its depth or exact alignment.

The client wanted crushed concrete retained on site for the redevelopment piling mat, requiring grading to specification rather than simple demolition arisings.

Our approach

The programme ran three work fronts concurrently from day one, with strip-out, structural demolition and slab processing progressing in parallel rather than sequentially. Crushing began while demolition continued elsewhere.

The fibre route was traced by survey and confirmed by hand-dug trial holes before any machine worked within ten metres of the indicated alignment. It was then protected with a marked and barriered corridor for the duration.

A mobile crushing and screening plant produced 4,100 tonnes of graded aggregate to the piling mat specification, tested and certified on site. This removed approximately 190 haulage movements from local roads and eliminated the imported fill requirement.

The site was handed over surveyed and levelled two days ahead of the contractual date.

Outcome

42,000 m²

Area cleared

5,200 t

Material processed

4,100 t

Aggregate retained on site

~190

Haulage movements avoided

2 days early

Handover

Plant deployed

Equipment mobilised against the engineered method for this programme. Where the correct machine was not in our own fleet, it was brought in rather than substituted.

  • High-reach demolition excavators
  • Mobile jaw crusher and screener
  • Hydraulic shears and pulverisers
  • Articulated dump trucks
  • Dust suppression cannons
Site record

Logistics Hub Structural Clearance — site record 1
Logistics Hub Structural Clearance — site record 2
Logistics Hub Structural Clearance — site record 3
Logistics Hub Structural Clearance — site record 4
Logistics Hub Structural Clearance — site record 5
Logistics Hub Structural Clearance — site record 6